Migration project · Phase 4 of 6

Phase 4: Execute

Prove the design works with a pilot, then copy data in waves while preparing users. By the end, the target holds validated data and people know what will change for them.

9 activities9 deliverables9 templates
Goals

What this phase achieves

  • Prove the runbook and tools with a pilot before the main migration.
  • Get users and change approvers to sign off that the target works.
  • Copy data in waves and keep it in sync until cutover.
  • Validate that what arrived matches what left.
  • Prepare staff so day one is not a surprise.
Activities

What to do, in order

  1. 1

    Run the pilot

    Migrate a small group, usually IT staff and willing early adopters, using the runbook exactly as written. Follow the Pilot test plan. For a mailbox move, check mail flow, calendars, delegates and mobile devices. For a file move, check permissions, sync clients and long paths. For a website, test on a staging URL or with a hosts file override. For a VM, run a test failover in an isolated network. Fix the runbook wherever reality differed.

  2. 2

    Run user acceptance testing

    Ask business users to work through the UAT test scripts and sign-off: open a shared mailbox, edit a file in a migrated library, run a month-end report against the migrated server, place a test order on the new shop. Record pass, fail and evidence, and fix failures before signing off.

  3. 3

    Raise and approve changes

    Submit a Change request (CAB) for each production change: batch start, DNS change, firewall rule, server shutdown. Include impact, timing, test evidence and the backout plan. Approval protects you and makes sure the help desk and other teams know what is coming.

  4. 4

    Communicate and train

    Send the emails in the User communication pack on the dates in the communication plan: announcement, what to expect, actions before the move, the evening before and day one. Publish the Quick-start guide for staff showing what changes, such as new sign-in, where files now live or reconfiguring a phone. Deliver the Training plan to the people who need more than a guide, such as power users and the service desk.

  5. 5

    Start the bulk copy

    Start the initial copy for each wave well ahead of its cutover date, then run incremental syncs so the final pass is small. Examples: create migration batches in Exchange Online (see create a migration batch), run the SharePoint Migration Tool or a third-party tool against file shares, replicate VMs with Azure Migrate or AWS Application Migration Service, copy a website and its database to the new host. Watch for throttling and errors daily.

  6. 6

    Validate the data

    Compare source and target in the Data validation report: mailbox item counts and sizes, file counts and total size per library, database row counts, page counts on the new site. Investigate every difference and record why it is acceptable or how it was fixed. Microsoft recommends checksums, row counts and file counts as validation checks for workload migrations.

  7. 7

    Prepare website search signals

    For a website move, work through the pre-launch part of the SEO migration checklist: crawl the old site, record rankings and top pages, build and test the redirects from the design phase, prepare the new XML sitemap and confirm canonicals and analytics on staging.

  8. 8

    Report progress daily

    Send a short Daily status report during active migration: what moved, what failed, open issues and what happens next. It keeps sponsors informed without extra meetings and builds the evidence for the go / no-go decision.

  9. 9

    Repeat for each wave

    After each wave, review what went wrong, update the runbook and communication pack, and confirm the next wave is still ready. Do not start a new wave while the previous one still has unresolved critical issues.

Deliverables

What you produce

DeliverableFree template
Pilot scope, tests and sign-offPilot test planDOCX
User acceptance results and sign-offUAT test scripts and sign-offXLSX
Approved change requestsChange request (CAB)DOCX
Daily progress and issue reportDaily status reportDOCX
Staff emails from announcement to day oneUser communication packDOCX
Day-one guide for staffQuick-start guide for staffDOCX
Training schedule and attendanceTraining planXLSX
Source versus target comparisonData validation reportXLSX
Website search and redirect checksSEO migration checklistXLSX
Phase gate

Before you move to Cut over

Tick these off with the project sponsor. If any are not true, stay in this phase.

Who is involved

Roles in this phase

RoleResponsibility
Migration engineersRun batches, copies and replication, monitor errors and update the runbook.
Test lead and UAT testersRun the pilot and acceptance tests and record evidence.
Change advisory boardReviews and approves production changes.
Communications leadSends the user communication pack on schedule.
Trainers and championsDeliver training and help colleagues on day one.
Project managerPublishes the daily status report and manages issues and risks.
SEO lead or web agencyOwns redirects, sitemaps and search checks for website moves.
Pitfalls

Common mistakes and how to avoid them

Treating the pilot as a formality

Pick pilot users who will actually test, give them scripts, and be willing to delay if it fails.

Starting the bulk copy too late

Large mailboxes, file shares and VM disks take time to copy. Start early and use incremental syncs so cutover is a small final pass.

Trusting the tool report alone

Compare counts and sizes yourself and spot-check content, permissions and metadata with real users.

Communications that arrive with the change

Send notices in advance on the agreed dates, and tell people what they need to do, not just what IT is doing.

Forgetting the service desk

Brief and train the help desk before the first wave. They take the calls.

Changing the design mid-wave

Log requested changes and apply them between waves through the decision log, not during an active migration.

FAQ

Questions

How big should the pilot be?

Large enough to cover each kind of user and data you will migrate, such as a shared mailbox, a delegate, a mobile user and a large file library, but small enough to roll back easily.

What should I validate after copying data?

Counts and sizes at minimum: mailbox items, file counts, database rows or page counts. Then spot-check permissions, metadata and a sample of real content with the owners.

Can users keep working during the bulk copy?

Usually yes. Most mail, file and VM replication tools copy in the background and then sync changes, so users keep working in the source until cutover.

Do I need change board approval for a small migration?

If your organisation has a change process, use it. If not, at least write down the change, its timing and its backout steps, and tell the people affected.