Azure migration: how to move servers, databases and files to Azure
A start-to-finish plan for moving on-premises workloads to Azure: assess, choose a route for each workload, build the landing zone, connect network and identity, replicate, test, cut over and optimise.
Your migration plan
This moves on-premises workloads into Azure in planned waves. Azure Migrate (Microsoft's migration hub) discovers your servers, databases and web apps, checks readiness and suggests sizes. You then pick a route for each workload: rehost (lift and shift) servers to Azure VMs, move SQL Server databases to Azure SQL, move file shares to Azure Files, and move suitable web apps to App Service. The time depends on how many workloads you have, how long you collect performance data and how fast your link to Azure is. The copies run in the background; each outage is only the final switch.
One Microsoft project covers discovery, sizing, cost and server replication, and rehosting is the lowest-risk way to leave a data centre. Managed services remove patching work where the change is small.
Other options and when to use them
- Rehost everything to Azure VMs, modernise later: You have a hard deadline such as a data centre exit or hardware end of life, and little time for testing application changes.
- Azure VMware Solution: You must keep vSphere, vCenter tooling or VMware-only appliances, or need to move faster than you can convert VMs.
- A migration partner or a third-party tool listed by Microsoft: You lack in-house Azure skills, or need features outside Azure Migrate. Partner tools may charge for their services.
Assess first, build the foundation second, and move workloads last in small waves, simple and non-production systems before critical ones. Each step depends on the one before: sizing needs performance data, and a migrated server only works if the network, DNS and sign-in it depends on already exist in Azure.
- Discovery and assessment in an Azure Migrate projectReadiness, size and dependencies decide the route and the wave for every workload. Without them every later step is a guess.
- Business case and route per workload (rehost, replatform, retire, replace, retain)Retiring or replacing workloads early means less to copy, test and pay for.
- Landing zone: subscriptions, policies, budgets and admin accessMicrosoft says to set subscription boundaries before workloads move. Moving resources between subscriptions later is extra work.
- Hybrid network, DNS and identity reachable from AzureMicrosoft calls hybrid connectivity one of the few prerequisites that can block every workload at once. Servers also need DNS and domain sign-in after cutover.
- Pilot: development, test and low-risk internal workloadsMicrosoft recommends non-production and low-complexity workloads first, to prove the process before production.
- Production waves, each application with its servers, databases and shares togetherMicrosoft warns that dependent workloads cause outages if they are not migrated together.
- Critical systems last, then optimisation and decommissioningCritical systems move once the team has proven the method. Source servers go only after the rollback window closes.
Built-in and third-party tools treat these differently. Tick each one off once you have decided.
Download this checklist (Excel)How each tool handles it
Built-in methodAzure Migrate assessment: reports readiness and recommended targets for servers (Azure VMs), SQL Server (Azure SQL Database, Managed Instance or SQL Server on Azure VMs) and web apps (App Service, Azure Spring Apps or AKS). The business case maps workloads to migration strategies. It does not decide for you.Tip: Record the route and the reason for each workload in a 7R decision matrix, and get the application owner to agree it.
Microsoft Learn: Select your cloud migration strategiesHow each tool handles it
Built-in methodAzure Migrate assessment: offers as-is or performance-based sizing. The comfort factor adds a buffer to CPU, memory, disk and network sizing. Microsoft's example: a 10-core VM at 20% use normally becomes a 2-core VM, or 4 cores with a comfort factor of 2.0.Tip: Collect performance data over a full business cycle, including month-end, before you trust a performance-based size.
Microsoft Learn: Azure Migrate assessment overviewHow each tool handles it
Built-in methodAzure Migrate: the project geography stores discovered metadata only, and you can migrate to other regions. For agent-based (physical) migration, the target region cannot be changed after you select Create resources, and all later migrations in that project go to that region.Tip: Agree the region against your data residency rules first, and use a separate project for a second region.
Microsoft Learn: Migrate machines as physical servers to AzureHow each tool handles it
Built-in methodMicrosoft: choose on throughput, latency, compliance, lead time and routing, not on how new you are to Azure. VPN Gateway is often the fastest path; avoid the Basic SKU for production migrations. ExpressRoute depends on a provider and can take weeks or months.Tip: If ExpressRoute will not be ready in time, start with VPN Gateway and keep it as the backup path later.
Microsoft Learn: Azure landing zones for on-premises expertsHow each tool handles it
Built-in methodMicrosoft: workloads that need LDAP, Kerberos or Group Policy need an early decision on domain controllers or Active Directory sites in Azure before cutover. Admins need Microsoft Entra ID groups and an emergency access path first.Tip: Test domain sign-in from a VM in the Azure network during the pilot, before any production wave.
Microsoft Learn: Azure landing zones for on-premises expertsHow each tool handles it
Built-in methodAzure Migrate agentless (VMware): independent disks and iSCSI targets are not supported, and RDM (raw device) or passthrough disks are not replicated. Encrypted disks, shared disk clusters and NFS volumes mounted inside the guest are not supported by agentless or agent-based. Hyper-V: passthrough, shared, FC and iSCSI disks are not supported, and BitLocker must be turned off first.Azure Migrate agent-based migration (VMware)Supports independent disks, passthrough disks and iSCSI targets, up to 63 disks per VM. Needs a replication appliance and the Mobility service on each VM.Tip: Add disk type, encryption and clustering columns to the inventory and flag servers before you plan waves.
Microsoft Learn: Support for Hyper-V migrationHow each tool handles it
Built-in methodAzure Migrate (VMware agentless and agent-based, and Hyper-V): OS disks up to 2 TB for Generation 1 VMs and data disks up to 32 TB. Generation 2 OS disks up to 4 TB, but Microsoft's Hyper-V page also lists 2,048 GB, so check before you rely on it. Hyper-V: up to 16 disks per VM.Tip: Shrink or split oversized disks, or move that data separately, before the server's wave.
Microsoft Learn: Support for Hyper-V migrationHow each tool handles it
Built-in methodAzure Database Migration Service: offline only to Azure SQL Database; online or offline to Managed Instance and SQL Server on Azure VMs. Managed Instance link (needs Azure Arc on the SQL Server): replicates in near real time, so downtime is the final cutover only.Tip: Use the decision helper and the SQL Server playbook for each instance; logins and SQL Agent jobs need separate handling.
Microsoft Learn: Migrate from SQL Server overviewHow each tool handles it
Built-in methodMicrosoft rates Azure File Sync, Azure Storage Mover, Robocopy and Azure Data Box as full fidelity for Azure file shares. AzCopy may lose some fidelity and is limited to 10 million files per job. Azure Files cannot store alternate data streams, and LastAccessTime always equals CreationTime.Azure Storage MoverKeeps folder structure, timestamps, ACLs and attributes for SMB shares, and re-runs copy only what changed.Tip: Set the permissions on the root of each Azure file share before the bulk copy; Microsoft warns root changes made afterwards can take a long time.
Microsoft Learn: Migration overview for SMB Azure file sharesHow each tool handles it
Built-in methodAzure File Sync: syncs a Windows Server 2016 or later NTFS volume to an Azure file share and can tier cold files to the cloud. It skips hard links, symbolic links and junctions, never syncs files such as thumbs.db or *.tmp, and Microsoft says databases are not a good workload for it.Azure Storage MoverCopies straight from NAS or Linux SMB 2 and 3 shares, and NFS 3 and 4 shares, to Azure Files when there is no Windows server to run Azure File Sync.Tip: Keep around 20 to 30 million items or fewer per share, as Microsoft suggests for Azure File Sync.
Microsoft Learn: Plan an Azure File Sync deploymentHow each tool handles it
Built-in methodAzure Hybrid Benefit: needs core licences with active Software Assurance or qualifying subscription licences, and at least 8 core licences per VM. Standard licences can run on-premises and in Azure at the same time only once, for up to 180 days, while you migrate.Tip: Count licences with your licensing partner before you tick Azure Hybrid Benefit in Azure Migrate.
Microsoft Learn: Azure Hybrid Benefit for Windows ServerHow each tool handles it
Built-in methodWindows Server 2016 reaches end of support on 12 January 2027. ESU for it can be set up through Azure Arc, with billing from 13 January 2027. Microsoft says Azure VMware Solution machines and VMs on Azure Local are eligible for free ESU and should not enrol through Azure Arc.Tip: Flag every 2016 server in the assessment and decide its path before you place it in a wave.
Microsoft Learn: Prepare to deliver ESUs through Azure ArcHow each tool handles it
Built-in methodMicrosoft: set rollback criteria and procedures before any migration starts, test rollback in a non-production environment, and get written approval from stakeholders for the plan and the rollback procedure.Tip: Write the rollback triggers into the cutover runsheet and name who can call a rollback.
Microsoft Learn: Plan your migration
- 1
Assess
Over a full business cycleWatch out: Azure Migrate appliance: one appliance discovers up to 10,000 VMware servers, 5,000 Hyper-V servers or 1,000 physical servers, and registers with one project only.
Ways around it
- Deploy more appliances in the same project for larger estates.
Show the detailed steps (5) →Watch out: Azure Migrate business case: available in public cloud regions only, not Azure Government.
Ways around it
- In Azure Government, use the assessments for size and cost estimates instead.
- 2
- 3
Connect network and identity
Watch out: ExpressRoute depends on a connectivity provider, and Microsoft says to plan in weeks or months.
Ways around it
- Start with VPN Gateway and keep it as the backup path once ExpressRoute is live.
Check your DNS records before and after the change
Show the detailed steps (4) → - 4
Pilot
Show the detailed steps (3) →Watch out: Azure Migrate agentless replication (VMware) does not copy RDM, passthrough or independent disks, or in-guest iSCSI targets.
Ways around it
- Test-migrate every flagged server and check each volume is there.
Tools that can do it
- Azure Migrate agent-based migration (VMware)Supports independent disks, passthrough disks and iSCSI targets. Needs a replication appliance and the Mobility service on each VM.
- 5
Migrate in waves
Watch out: Azure Migrate: you select up to 10 machines at a time for replication (stated for Hyper-V).
Ways around it
- Split each wave into batches of 10 in the wave plan.
Watch out: AzCopy may lose some file fidelity because it uses the Azure Files REST API, and handles up to 10 million files per job.
Ways around it
- Use AzCopy for small or simple shares only, and check permissions after the copy.
Tools that can do it
- Azure Storage MoverFull-fidelity SMB copies with ACLs, timestamps and attributes; re-runs copy only changes.
Show the detailed steps (3) →Watch out: Azure Database Migration Service: migration to Azure SQL Database is offline only, so writes stop for the whole copy.
Ways around it
- Choose Azure SQL Managed Instance with Managed Instance link if the database cannot stop for long.
- 6
Cut over
In each planned change windowWatch out: Azure Migrate (servers): migrated VMs take new private IP addresses, so hard-coded IPs and cached DNS keep clients on the old server.
Ways around it
- Search application settings for IP addresses during the test migration, and lower TTLs first.
Turn this phase into dated tasks with the cutover planner
Show the detailed steps (3) → - 7
Optimise and clean up
After the rollback windowShow the detailed steps (3) →Watch out: Azure Advisor: looks at 7 days of data by default, so a new VM's resize advice can miss month-end peaks.
Ways around it
- Change the lookback period to 30, 60 or 90 days before you act on resize advice.
- Every workload in the wave plan is migrated, retired or recorded as retained, with owner sign-off.
- Applications work from Azure, and names, drive mappings and connection strings point at Azure.
- Every migrated workload has backup, updates and security monitoring, and a budget with alerts.
- Source servers are off, no client still connects to them, and replication is completed.
Tools named in this plan are independent third-party products, not endorsed by the platform vendor and not paid placements. Check the tool's own documentation and run a pilot first.
Detailed steps
Open a part when you reach it in the plan. Each step says where to go, what to do and what you should see.
About this migrationWhat it covers, limits at a glance
An Azure migration moves the servers, databases, file shares and web apps you run on your own hardware into Microsoft Azure. Most organisations do not move everything the same way. Some servers are rehosted (lift and shift: copied to Azure virtual machines with as few changes as possible). Others are replatformed onto services Microsoft runs for you, such as Azure SQL Managed Instance, Azure Files and Azure App Service. Some are retired, replaced by software as a service, or kept where they are.
Azure Migrate is the starting point. It finds what you have, checks whether each workload is ready for Azure, suggests sizes and estimated running costs, builds a business case and then copies servers across. Before anything moves, you build a landing zone (the governed Azure foundation of subscriptions, policies, networks and access that workloads land in) and connect it to your network and directory.
This page is the hub. Each workload type has a deeper playbook: VMware, Hyper-V and physical servers to Azure, SQL Server to Azure SQL, NAS and file servers to Azure Files and Active Directory to Microsoft Entra ID. Still choosing a cloud? See cloud platforms compared.
1What you need before step one
| Need | Details | Where to get it |
|---|---|---|
| Azure subscription and roles | Owner or Contributor on the subscription that holds the Azure Migrate project, plus rights to create networks and resource groups. | Azure portal, https://portal.azure.com |
| Admin access to the sources | vCenter, Hyper-V host or server admin credentials for discovery, SQL Server credentials for SQL discovery, and share-level admin on file servers or NAS. | Your hypervisor, server and NAS consoles |
| Appliance machine | A VM or server for the Azure Migrate appliance. Microsoft lists 32 GB RAM, 8 vCPUs and about 80 GB of disk for VMware and physical, with internet access. | Set up the Azure Migrate appliance |
| Azure CLI (optional) | For the network, storage and Advisor commands in this guide. Azure Cloud Shell in the portal already has it. | Install the Azure CLI |
| AzCopy (optional) | For small file copies to Azure Files or Blob storage. | Copy files with AzCopy |
| Licence records | Windows Server and SQL Server licences, with Software Assurance or subscription status, for Azure Hybrid Benefit. | Your licensing partner or Microsoft licensing portal |
| Templates | Application inventory and dependency map, Workload 7R decision matrix, Business case and ROI, Migration wave plan, Network and DNS worksheet, Cutover runsheet. | Templates linked at the end of this guide |
2Discover and assess with Azure Migrate5 steps
Azure Migrate discovery is agentless: you install nothing on the servers. One appliance collects configuration, performance, installed software, SQL Server and dependency data and sends it to your project.
- 1
Create the project
Where: Azure portal (https://portal.azure.com) > search Azure Migrate > Get startedCreate a project in a resource group, and choose the geography where its discovered metadata is stored. Microsoft says the geography is only for metadata: you can still assess and migrate to other regions. Full steps are in set up the Azure Migrate appliance.
You should see: The project opens with Azure Migrate: Discovery and assessment available. - 2
Deploy the appliance and start discovery
Where: Azure Migrate project > Discover, then vSphere Client, a Hyper-V host or a Windows Server 2022/2025 machine, then https://appliance-name-or-IP-address:44368Download the OVA (VMware), VHD (Hyper-V) or PowerShell installer (physical and other clouds). Register the appliance with the project key, add credentials for vCenter, hosts or servers, and add SQL Server credentials so databases are discovered too. Select Start discovery. One appliance discovers up to 10,000 VMware servers, 5,000 Hyper-V servers or 1,000 physical servers.
You should see: Discovered servers, SQL Server instances and (for VMware and physical) ASP.NET web apps appear in the project. - 3
Let performance data build up
Where: The appliance (leave it running) and the project in the Azure portalLeave the appliance running over a representative period, including month-end or seasonal peaks. Assessments are a point-in-time snapshot, and performance-based sizing is only as good as the data behind it.
You should see: Servers show performance data and the appliance stays connected. - 4
Create assessments
Where: Azure Migrate project > Infrastructure tab > select workloads > Create assessmentAssess servers for Azure VMs, SQL Server for Azure SQL targets and web apps for App Service. Choose the target region, sizing (performance-based or as-is) and comfort factor (a buffer for peaks and growth). Microsoft calculates readiness first: a server that fails readiness is marked unsuitable and gets no size or cost.
You should see: Each assessment lists readiness, a recommended size and an estimated monthly cost per workload. - 5
Map dependencies
Where: Azure Migrate project > dependency analysis for the discovered serversUse agentless dependency analysis to see which servers talk to each other. Microsoft says dependent workloads cause outages if they are not migrated together, and to group them when in doubt.
You should see: Every server is assigned to an application group in your dependency map.
3Build the business case and choose a route per workload3 steps
| Workload | Common route | Tool | Deeper guide |
|---|---|---|---|
| VMware VMs | Rehost to Azure VMs | Azure Migrate agentless replication | VMware to Azure |
| Hyper-V VMs | Rehost to Azure VMs | Azure Migrate with the Hyper-V Replication provider on each host | VMware to Azure (Hyper-V section) |
| Physical servers, Xen, KVM, AWS or Google Cloud VMs | Rehost to Azure VMs | Azure Migrate agent-based replication with a replication appliance | VMware to Azure (physical section) |
| SQL Server | Replatform to Azure SQL Managed Instance or Azure SQL Database, or rehost to SQL Server on an Azure VM | Managed Instance link, Azure Database Migration Service, backup and restore | SQL Server to Azure SQL |
| File servers and NAS shares | Replatform to Azure Files, optionally with a local cache | Azure File Sync, Azure Storage Mover, Robocopy, Azure Data Box, AzCopy | NAS to Azure Files |
| ASP.NET web apps on IIS | Replatform to Azure App Service | Azure Migrate web app migration or App Service Migration Assistant | This guide, step 8 |
| Windows Server 2016 servers | Upgrade during or before the move, or cover with ESU | Azure Migrate, in-place upgrade, Azure Arc ESU | Windows Server 2016 end of support |
| Active Directory | Keep domain controllers for legacy apps; move users and devices to Entra ID over time | Entra Connect, domain controllers on Azure VMs | Active Directory to Entra ID |
- 1
Build the business case
Where: Azure Migrate project > Business case (preview) > Build business caseChoose Modernize with PaaS (prefers managed services) or Migrate to all IaaS (lift and shift). The business case compares on-premises and Azure total cost of ownership over several years and includes savings from Azure Hybrid Benefit and Extended Security Updates. Many on-premises costs are Microsoft defaults; replace them with your real figures in the assumptions. Check the vendor's current pricing for anything you quote.
You should see: A business case with cost comparison, cash flow, support status of your operating systems and databases, and suggested quick wins. - 2
Pick a route for each workload
Where: Your Workload 7R decision matrix, using the assessments and business caseMicrosoft's strategies are: retire (switch off), rehost (move with minimal changes), replatform (move to a managed platform with minimal code changes), refactor, rearchitect, rebuild, replace (with software as a service) and retain (leave as is). Use the table below for the common routes, and the decision helpers for which Azure SQL target and which VMware exit path.
You should see: Every workload has one route, a target service and an owner who agreed it. - 3
Plan waves
Where: Your Migration wave planPut development, test and low-risk internal workloads in the first waves, and critical systems later. Microsoft suggests adding one or two complex workloads to early waves to expose problems, planning only the next wave in detail, and avoiding busy business periods such as financial close.
You should see: A wave plan with dates, workloads, owners and change windows for at least the next wave.
4Build the landing zone3 steps
Microsoft defines an Azure landing zone as two parts: a platform landing zone (shared governance, security and services, usually one per Entra tenant) and a workload landing zone for each workload (its development, test and production environments).
- 1
Set subscription boundaries
Where: Azure portal > Management groups and Subscriptions, recorded in your Target-state architectureDecide the management group hierarchy and which subscriptions hold shared services (connectivity, identity, management) and which hold workloads. Microsoft says this is the decision that matters before workloads migrate. A subscription per workload makes cost allocation easier but is not required.
You should see: A documented hierarchy with platform and workload subscriptions created. - 2
Deploy from an accelerator
Where: Microsoft Learn: Cloud Adoption Framework > Azure landing zone > implementation optionsMicrosoft says its accelerators (infrastructure as code templates for platform and workload landing zones) are the fastest path for most organisations. Deploy with Bicep, Terraform or another repeatable method rather than one-off portal changes, so the next environment matches.
You should see: The landing zone deploys and its resources show in the platform subscriptions. - 3
Apply a small policy baseline and budgets
Where: Azure portal > Policy > Assignments, and Cost Management > BudgetsApply only the policies that prevent risk during migration: restrict allowed regions, deny unmanaged public internet exposure and require diagnostic settings for central logging. Set budgets and alerts with a named owner. Do not let a perfect tagging scheme delay the build.
az group create --name rg-migrate --location <region> az consumption budget list --output tableYou should see: Policy compliance shows the baseline assigned, and each workload subscription has a budget with alerts.
5Connect networking and identity4 steps
- 1
Create the networks
Where: Azure Cloud Shell or a terminal with the Azure CLI signed in (install the Azure CLI)Create a hub virtual network for shared connectivity and spoke virtual networks for workloads, with subnets per tier, plus an isolated network for test migrations. Microsoft warns against one network with one subnet holding everything. Check nothing overlaps your on-premises address ranges.
az network vnet create --resource-group rg-migrate --name vnet-workloads --address-prefix 10.20.0.0/16 --subnet-name snet-servers --subnet-prefix 10.20.1.0/24 az network vnet create --resource-group rg-migrate --name vnet-test --address-prefix 10.99.0.0/16 --subnet-name snet-test --subnet-prefix 10.99.1.0/24You should see: Each command returns JSON with "provisioningState": "Succeeded". - 2
Connect your sites
Where: Azure portal > Virtual network gateways (VPN Gateway) or ExpressRoute circuitsChoose VPN Gateway or ExpressRoute on throughput, latency, compliance and lead time. Microsoft says not to use the Basic VPN SKU for production migrations, and that ExpressRoute can take weeks or months to arrange, so run a VPN in parallel if dates are fixed.
You should see: From an on-premises server you can reach the private IP address of a test VM in Azure. - 3
Make DNS work both ways
Where: Your DNS servers (DNS Manager on a domain controller) and Azure portal > Private DNS zones or DNS private resolversMake on-premises names, Azure private DNS zones and any private endpoints resolve from a spoke network, and name an owner for forwarders and zones.
Resolve-DnsName app01.contoso.comYou should see: The same name resolves to the right address from on-premises and from a VM in Azure. - 4
Decide on domain controllers and admin access
Where: Microsoft Entra admin center (https://entra.microsoft.com) > Groups, and your Target-state architectureCreate Entra ID groups for platform admins and an emergency access account. For servers that still need Kerberos, LDAP or Group Policy, decide whether domain controllers and Active Directory sites must exist in Azure before cutover. The longer-term move of users and devices is in Active Directory to Entra ID.
You should see: A test VM in Azure can join the domain and a domain user can sign in to it.
6Move servers: replicate, test and migrate3 steps
Rehosting copies each server's disks to Azure in the background, lets you test a copy, then switches over in a short outage. The click-by-click steps are in the VMware, Hyper-V and physical servers to Azure playbook.
- 1
Start replication
Where: Azure Migrate project > Execute > Migration > Start executionVMware: choose agentless migration through the discovery appliance. Hyper-V: install the Hyper-V Replication provider on every host or cluster node. Physical servers, other hypervisors and other clouds: build a separate replication appliance (not the discovery appliance and not a source server) and install the Mobility service on each server. Choose the size, disk type, network and Azure Hybrid Benefit for each VM.
You should see: The servers appear under Execute > Migrations with initial replication in progress. - 2
Run a test migration
Where: Azure Migrate project > Execute > Migrations > the server > Testing > Start test migrationAlways test into the isolated test network, because the test VM is a full copy with the same name. Sign in, check services and run the application's smoke tests. Then select Clean up test migration.
You should see: The test VM boots in the test network and the smoke tests pass, or you have a list of fixes. - 3
Migrate in the change window
Where: Azure Migrate project > Execute > Migrations > the server > Completion > MigrateStop the application, choose to shut down the source so a final copy runs, and select Migrate. Then update DNS and firewall rules for the new private IP address.
You should see: The server shows at the Completion stage and the application answers from Azure.
7Move SQL Server databases3 steps
A SQL Server can move with its VM (rehost), or its databases can move to a managed Azure SQL service (replatform). The choice decides the tool. Use the Azure SQL target helper and the SQL Server to Azure SQL playbook for the full steps.
- 1
Confirm the target from the assessment
Where: Azure Migrate project > Assessments (SQL), or SQL Server enabled by Azure Arc > Migration assessmentCheck readiness for Azure SQL Database, Azure SQL Managed Instance and SQL Server on Azure VMs, and the recommended service tier and size for each.
You should see: Each database has a target and a size, and every blocker is recorded. - 2
Choose the copy method
Where: Your Technical migration runbook, using Microsoft Learn: Migrate from SQL Server overviewManaged Instance link (needs Azure Arc on the SQL Server) replicates in near real time to Managed Instance, so downtime is only the final cutover. Azure Database Migration Service does offline copies to all three targets and online copies to Managed Instance and Azure VMs. Backup and restore to SQL Server on an Azure VM is offline: downtime lasts until the restore finishes.
You should see: Each database has a copy method that fits its allowed downtime. - 3
Move logins and jobs, then cut over
Where: SQL Server Management Studio connected to the target, then the application configurationRecreate logins, SQL Agent jobs and other server-level objects on the target before cutover, then stop writes, complete the copy and change connection strings.
You should see: The application connects to the Azure database and its smoke tests pass.
8Move file shares to Azure Files3 steps
Azure Files gives you SMB file shares in Azure. Decide first whether users keep a local cache (hybrid, with Azure File Sync) or connect to Azure directly (cloud-only). The NAS to Azure Files playbook has the full steps, including sign-in with Active Directory.
- 1
Pick the copy tool per source
Where: Microsoft Learn: Migration overview for SMB Azure file shares (tool table)Windows Server 2016 or later: install Azure File Sync in place. NAS or Linux SMB shares: Azure Storage Mover (SMB 2 and 3; SMB 1 is not supported) or Robocopy. Very large data over a slow link: Azure Data Box (offline, by shipping a device). AzCopy suits small, simple copies only, because Microsoft says it may lose some file fidelity and handles up to 10 million files per job.
You should see: Each share has a tool and a target Azure file share in your inventory. - 2
Set root permissions, then copy
Where: Azure portal > Storage accounts > your account > File shares, then the tool you choseSet the Windows ACLs on the root of each share before the bulk copy. Microsoft warns that root permission changes made after a large copy can take a long time to apply. For a quick one-off copy with AzCopy, see copy files with AzCopy.
azcopy copy 'C:\myDirectory' 'https://mystorageaccount.file.core.windows.net/myfileshare?<SAS-token>' --recursive --preserve-permissions=true --preserve-info=trueYou should see: Files appear in the Azure file share with their folders, timestamps and permissions. - 3
Top up and switch
Where: The copy tool, then DFS Namespaces, Group Policy drive maps or your login scriptsRun repeat copies so only changes move (Robocopy /MIR, Storage Mover re-runs, or Azure File Sync), make the source read-only, run a final pass, then repoint drive mappings and paths.
You should see: Users open their files from the Azure file share and the source share is read-only.
9Move web apps to Azure App Service3 steps
- 1
Assess the web apps
Where: Azure Migrate project > Infrastructure > web apps > Create assessmentThe appliance discovers ASP.NET web apps on IIS (VMware and physical environments). Assess them for Azure App Service. Apps rated ready or ready with conditions can be migrated in bulk.
You should see: Each web app shows a readiness rating and a recommended App Service plan. - 2
Migrate with Azure Migrate or the migration assistant
Where: Azure Migrate project > Execute > Migration (web apps), or the App Service Migration Assistant from Microsoft Learn: Migrate .NET apps to Azure App ServiceFor many apps in a VMware estate, use Azure Migrate's at-scale web app migration, which Microsoft says handles up to five App Service plans per run. For apps on a single Windows server, use the App Service Migration Assistant or its PowerShell scripts, linked from Microsoft's page.
You should see: The app runs on an azurewebsites.net address in App Service. - 3
Test, then move the domain
Where: Azure portal > App Services > your app > Custom domains, then your DNS hostTest the app on its azurewebsites.net address, add your custom domain and certificate in App Service, then change the DNS record in the change window.
You should see: The site answers on your own domain from App Service with a valid certificate.
10Cut over each wave3 steps
- 1
Agree go/no-go and rollback
Where: Your Cutover runsheet and Rollback planMicrosoft says to set rollback criteria and procedures before any migration, get written stakeholder approval and name who can decide on a rollback. Schedule cutovers in maintenance windows or off-peak hours.
You should see: A signed runsheet with go/no-go criteria, rollback triggers and a named decision-maker. - 2
Lower DNS TTLs
Where: Your DNS server or DNS host (lower DNS TTL before a migration)Lower the TTL on every record you will change a few days before the window, so clients pick up the new addresses quickly.
You should see: The records show the lower TTL when you query them. - 3
Switch and test
Where: Azure Migrate, the database and file tools you chose, then DNS and application settingsStop the application, run the final copy for each server, database and share in the wave, then repoint DNS, connection strings and drive mappings. Run acceptance tests with each owner.
You should see: Every owner signs off, or the agreed rollback trigger is met and you roll back.
11Optimise and decommission3 steps
- 1
Protect and operate
Where: Azure portal: Backup center, Azure Update Manager, Microsoft Defender for CloudTurn on backup, update management and Defender for Cloud for every migrated VM, database and share, and confirm a first backup completes.
You should see: Each workload shows a backup policy with a completed backup and appears in Update Manager. - 2
Right-size with Azure Advisor
Where: Azure portal > Advisor > Cost, or Azure Cloud ShellAdvisor suggests resizing or shutting down underused VMs. It looks at 7 days of data by default; change the lookback to 30, 60 or 90 days under Configuration > Resources > VM/Virtual Machine Scale Sets right sizing so month-end peaks count. Its savings use retail rates and ignore reservations and savings plans.
az advisor recommendation list --category Cost --output tableYou should see: A list of cost recommendations you can action or dismiss with a reason. - 3
Complete and decommission
Where: Azure Migrate project > Execute > Migrations > Complete migration, then your hypervisor, backup console and CMDBAfter the rollback window, complete each migration so replication stops. Power off and remove source servers, remove them from backup jobs, and update documentation.
You should see: No source server is running, and nothing in Azure Migrate still shows active replication.
Expert notes
The detail behind the plan: options compared, and what experienced engineers check first. Tap any item.
Compare all the ways to do this3 options
Rehost with Azure Migrate (lift and shift)
Medium effortBest for: Most servers, and any estate with a deadline such as a data centre exit or hardware end of life
- Fast and low risk, with minimal changes to each server
- One project covers discovery, sizing and replication, with a test migration before cutover
- You still patch and manage every operating system
- Some disk types and encrypted disks need another method or preparation
Replatform to managed services (Azure SQL, Azure Files, App Service)
Medium effortBest for: SQL Server databases, file shares and ASP.NET web apps that pass the assessment
- Microsoft runs the platform, so there is less patching and maintenance
- Online copy methods such as Managed Instance link keep downtime to the final switch
- Each service has features it does not support, found in assessment and testing
- Logins, jobs, drive mappings and connection strings must be changed
Azure VMware Solution
High effortBest for: VMware estates that must keep vSphere tooling or VMware-only appliances
- VMs move without conversion and keep vCenter
- Microsoft says its VMs are eligible for free Windows Server 2016 ESU
- Runs on dedicated hosts, a larger commitment than individual VMs
- Does not reduce your dependence on VMware
Rehost most servers with Azure Migrate, and replatform databases, file shares and web apps where the assessment shows they are ready, because that removes patching work for little change. Choose Azure VMware Solution only when you must keep vSphere; compare it in the VMware exit path helper.
Retire and replace before you migrateCost lever
Every server you move is copied, tested and paid for in Azure. Microsoft lists retire (switch off workloads with no business value) and replace (use a SaaS product) as strategies alongside rehost.
Use the software inventory and dependency data from Azure Migrate to find servers nobody uses, and agree with owners which to switch off before wave planning.
Size on performance over a full business cycleCost lever
On-premises servers are often given more CPU and memory than they use. As-is sizing carries that into Azure. Performance-based sizing is only as good as the data, and assessments are a point-in-time snapshot.
Let the appliance run through month-end or seasonal peaks, use performance-based sizing with a comfort factor, and compare the result with known peaks before accepting it.
Replace the business case defaults with your own figuresCost lever
The Azure Migrate business case uses Microsoft default assumptions for on-premises hardware, storage, facilities and labour. It also assumes servers left on-premises are Azure Arc-enabled unless you turn that off.
Open the assumptions and enter your real costs, migration cadence and region before you share the result. Treat it as an estimate and check the vendor's current pricing.
Start the network link earlySaves time
Microsoft calls hybrid connectivity one of the few prerequisites that can block every workload at once. ExpressRoute depends on a provider and can take weeks or months.
Order ExpressRoute (if needed) when the project starts, and build a VPN Gateway (not the Basic SKU) so the pilot is not held up.
Move dependent systems in the same waveReduces risk
Microsoft says dependencies between workloads cause service disruptions if they are not migrated together. Splitting an application between your site and Azure adds delay to every call between its parts.
Use dependency analysis to group servers, databases and shares by application. When unsure, group them, and include the load balancers, DNS records and caches each group needs.
Check disks before choosing a replication methodReduces risk
Azure Migrate agentless replication does not support independent disks or iSCSI targets and does not replicate RDM or passthrough disks. A server can migrate and boot without one of its volumes.
Record disk type, encryption and clustering for every server, and test-migrate any flagged server to check every volume is present. Encrypted disks and shared disk clusters are not supported by either method, so decrypt or rebuild them.
The agent-based method installs the Mobility service in the guest, so it replicates the independent disks, passthrough disks and iSCSI targets that agentless replication cannot.
- Azure Migrate agent-based migrationMicrosoft lists independent disks, passthrough disks and iSCSI targets as supported. Needs a replication appliance and the Mobility service on each VM.
Use a full-fidelity tool for file sharesReduces risk
File permissions (NTFS ACLs), timestamps and attributes are what make a share usable after the move. Microsoft says AzCopy may lose some file fidelity because it uses the Azure Files REST API, and is limited to 10 million files per job.
Use Azure File Sync, Azure Storage Mover or Robocopy for production shares, and set root permissions on each Azure file share before the bulk copy.
These Microsoft tools keep ACLs, timestamps and attributes, and their repeat runs copy only what changed.
- Azure Storage MoverSMB 2 and 3 and NFS sources to Azure Files with ACLs, timestamps and attributes; re-runs move only changes, or only new metadata.
- Azure File SyncSyncs a Windows file server to Azure Files in the background with permissions intact.
Azure File Sync needs a Windows server with NTFSSaves time
Azure File Sync runs on Windows Server 2016 or later and supports only directly attached NTFS volumes. A NAS cannot run it, and it skips hard links, symbolic links and junctions.
For a NAS, copy straight to Azure Files, or copy to a Windows server first and sync from there. Keep shares to around 20 to 30 million items, as Microsoft suggests.
Storage Mover reads NAS and Linux shares directly, so no Windows server is needed in between.
- Azure Storage MoverCopies SMB 2 and 3 mounts to SMB Azure file shares and NFS 3 and 4 mounts to NFS Azure file shares. SMB 1 sources are not supported.
Plan for a slow link with offline transferSaves time
The first full copy of servers and shares goes over your connection to Azure. Microsoft lists Azure Data Box (shipping a device) as an option that takes longest because of shipping, but does not use your link.
Estimate total data against your upload speed in the pilot. For large file sets, seed with Data Box and top up online.
Data Box carries the bulk copy offline, and Storage Mover then copies only what changed since the Data Box transfer.
- Azure Data BoxMicrosoft says Data Box and Data Box Disk preserve ACLs, timestamps and attributes for SMB Azure file shares.
- Azure Storage MoverDetects differences after a Data Box transfer and uploads only new and changed files.
Count licences before you tick Azure Hybrid BenefitCompliance
Azure Hybrid Benefit needs Windows Server core licences with active Software Assurance or a qualifying subscription, at least 8 core licences per VM, and Microsoft can audit. Standard licences may run in both places only once, for up to 180 days, while you migrate.
Check licence counts and coverage dates with your licensing partner, apply the benefit only to covered VMs, and switch the source off within the allowance.
Decide the path for Windows Server 2016Compliance
Windows Server 2016 reaches end of support on 12 January 2027. ESU through Azure Arc is billed from 13 January 2027. Microsoft says Azure VMware Solution and Azure Local VMs are eligible for free ESU.
Flag 2016 servers in the assessment and choose: upgrade before or during the move, rebuild, or cover with ESU. See the Windows Server 2016 end of support guide.
Check it worked, or roll back
Full validation checklist8 checks
Run these before you declare the migration complete. Record the results in the data validation report.
| Check | How to check | What good looks like |
|---|---|---|
| Every workload in the wave is accounted for | Compare Azure Migrate > Execute > Migrations, your database and file copy logs, and App Service with the Migration wave plan. | Every workload is migrated, retired or recorded as retained; none is missing or still mid-copy. |
| Servers boot with all disks and the VM agent | In the Azure portal open each VM > Overview and Disks, then sign in with Bastion or RDP/SSH and check every volume is online. | The VM agent status is Ready and every disk from the inventory is present at the right size. |
| Names resolve to Azure | Run | Every name returns the Azure address from both places. |
| Domain sign-in works on migrated servers | On each migrated Windows VM, run | The command returns True and domain users can sign in. |
| Databases match the source | Compare row counts for key tables and run the application's data checks against the Azure database, recording results in the Data validation report. | Counts match and the application owner signs off the data. |
| File shares keep permissions | Open a sample of folders on the Azure file share from a user PC and check Properties > Security against the source. | Permissions, owners and timestamps match the source for the sample; users can open their files. |
| Protection and cost controls are on | Check Backup center for completed backups, Azure Update Manager for each VM, and Cost Management > Budgets for each subscription. | Every workload has a completed backup and every subscription has a budget with alerts. |
| Nothing still uses the source | Check firewall or server logs for connections to old server addresses and shares after cutover. | No client connects to the source systems. |
Rollback planIf it goes wrong
Roll back if
- A critical application fails acceptance tests after cutover and the fix is not found within the window
- A migrated server will not boot or is missing data
- Hybrid network or domain sign-in from Azure fails and cannot be fixed within the window
- Performance is well below the agreed baseline and resizing does not fix it
Point of no return
Rollback is simple while the source systems are intact and users have not written data in Azure: stop the Azure copy, start the source and revert DNS and connection strings. Once users write data in Azure, rolling back also means copying that data back. Completing a server migration in Azure Migrate stops replication, so migrating it again starts from scratch. Decommissioning or deleting a source server is the final point of no return.
- 1
Stop writes in Azure
Where: Azure portal: the VM, App Service app or databaseStop the application, then stop the VM or app so it cannot clash with the source. Note what data was written since cutover.
You should see: The Azure resource shows Stopped and no users can write to it. - 2
Start the source
Where: vSphere Client, Hyper-V Manager or the physical server, and SQL Server Management StudioPower on the source servers, start their services and make any read-only source databases or shares writable again.
You should see: The application answers on its original address. - 3
Revert names and settings
Where: Your DNS server or host, application configuration, DFS Namespaces or drive mapping Group PolicyPoint DNS records, connection strings and drive mappings back to the source.
You should see:Resolve-DnsNamereturns the source address and users open files from the original share. - 4
Repair domain trust if needed
Where: Elevated Windows PowerShell on the source serverIf the Azure copy ran on the domain, run
Test-ComputerSecureChannel. If it returns False, runTest-ComputerSecureChannel -Repair -Credential (Get-Credential).You should see: The command returns True and domain users can sign in. - 5
Copy back data and record the cause
Where: The application or database, then your Rollback planCopy data written in Azure since cutover back to the source, or get the data owner to accept the gap in writing. Record why you rolled back before rescheduling the wave.
You should see: The source holds every change, or the gap is signed off, and the wave has a new date.
Agree the triggers and who decides before the go / no-go meeting. Use the rollback plan template.
Common problems and fixes7 errors
Server marked not ready (unsuitable for Azure) in the assessmentCause: The server failed the readiness stage, for example an unsupported operating system or disk. Microsoft skips sizing and cost for such servers.
Fix: Open the readiness details, fix the issue (upgrade the OS, resize the disk) and recalculate, or choose another route for that server.
Hyper-V VM cannot be selected for replicationCause: Microsoft says VMs already enabled for Azure Site Recovery or Hyper-V Replica cannot be replicated by Azure Migrate.
Fix: Turn off the existing replication for that VM, then select it again.
Migrated VM boots but a drive is missingCause: Agentless replication does not copy RDM or passthrough disks, and NFS volumes mounted in the guest are not replicated by either method.
Fix: Use agent-based replication for RDM, passthrough or iSCSI disks, and move NFS data separately.
Cannot change the target region for the migration projectCause: For agent-based migration the region is fixed once you select Create resources.
Fix: Create a separate Azure Migrate project for workloads going to another region.
Azure File Sync cannot create a server endpoint on a volumeCause: Azure File Sync supports only directly attached NTFS volumes; ReFS, FAT and FAT32 are not supported.
Fix: Move the data to an NTFS volume, or copy it with Azure Storage Mover or Robocopy instead.
Files such as thumbs.db, desktop.ini or *.tmp are missing after Azure File SyncCause: Azure File Sync never syncs a fixed list of files, including these.
Fix: Expected behaviour: no fix needed. Check Microsoft's list before you report missing files.
Business case option missing in an Azure Government projectCause: Microsoft says the business case works only in public cloud regions.
Fix: Use the assessments for size and cost estimates in Azure Government.
Frequently asked questions
What is the first step in an Azure migration?
Discover and assess. Create an Azure Migrate project, deploy the appliance and let it collect performance and dependency data, then build assessments and a business case before you choose routes.
Is Azure Migrate free?
Microsoft describes Azure Migrate as a free service. You pay for the Azure resources you migrate into, and partner tools used with it may charge for their services.
What does lift and shift mean in Azure?
Lift and shift (rehost) copies a server to an Azure VM with as few changes as possible. Microsoft describes it as fast and low risk, for when you need little disruption and no near-term modernisation.
What is an Azure landing zone and do I need one?
It is the governed Azure foundation that workloads land in: subscriptions, policies, networks, access and logging. Even a small migration needs subscriptions, a network, DNS and admin access set up before the first server moves.
Can Azure Migrate move databases and file shares?
Azure Migrate discovers and assesses SQL Server and can discover file shares. Databases usually move with Managed Instance link, Azure Database Migration Service or backup and restore; file shares with Azure File Sync, Storage Mover or Robocopy.
Can I migrate from AWS or Google Cloud to Azure?
Yes. Azure Migrate treats VMs in other public clouds as physical servers and moves them with agent-based replication and a replication appliance.
How long does an Azure migration take?
It depends on the number of workloads, how long you collect performance data, your link speed and testing. Microsoft suggests planning only the next wave in detail and adding contingency time.