Migration project · Phase 1 of 6

Phase 1: Assess

Find out exactly what you have, who uses it and what it depends on, then decide whether and how each piece should move. Every later phase is built on what you learn here.

10 activities9 deliverables9 templates
Goals

What this phase achieves

  • Build a complete, owned inventory of the users, data, applications and servers in scope.
  • Map the dependencies that will break if one item moves without another.
  • Choose a migration approach for each workload: move as is, change platform, replace, keep or retire.
  • Identify licensing, security, compliance and network constraints before they become surprises.
  • Give the sponsor an evidence-based readiness verdict and a rough cost comparison to decide on.
Activities

What to do, in order

  1. 1

    Agree the scope question

    Write down, in one or two sentences, what the business wants to achieve and what is in and out of scope. "Move all mailboxes and the shared drive to Microsoft 365" or "Move the three line-of-business VMs off the ageing host" is enough to start. Without this, discovery never ends.

  2. 2

    Inventory what you have

    Export the facts from the systems themselves rather than asking people from memory. Examples:

    • Mailbox move: every mailbox, shared mailbox, archive, distribution list and resource, with size and item count.
    • File server move: every share, its size, file count, top-level folders, longest paths and owners.
    • Website move: every domain, page URL, form, plugin, integration and the email that runs on the same domain.
    • VM move: every server with OS version, CPU, memory, disk, IP address and what runs on it.

    Record each item in the Mailbox and data inventory or the Application inventory and dependency map.

  3. 3

    Find an owner for everything

    Every mailbox, share, site and application needs a named business owner who can answer "who uses this?" and approve its move or retirement. Items with no owner after reasonable effort are strong candidates to archive or retire, but get that decision in writing.

  4. 4

    Map dependencies

    Trace what each item talks to. A scanner that emails reports through an on-premises Exchange server, an accounting app that reads a mapped drive letter, a website contact form that sends through a mail relay, a VM that authenticates against a domain controller staying behind. Dependencies decide which items must move together in the same wave.

  5. 5

    Assess identity, licensing and security

    Check how users sign in today and how they will sign in after the move (for example Active Directory to Entra ID). List current licences and what the target needs. Record retention policies, litigation holds, data residency rules, MFA and conditional access so the design phase can carry them across. Use the Licensing assessment and Security and compliance assessment.

  6. 6

    Check the network and DNS

    Note who controls each domain and its DNS host, current MX, SPF, DKIM and DMARC records, available bandwidth for bulk copies, and any firewall or proxy that will block migration traffic. Losing access to a DNS registrar account is a common and avoidable cause of delay.

  7. 7

    Decide a path for each workload

    Use the Workload 7R decision matrix to give every item one of: rehost, replatform, refactor, repurchase, retire, retain or relocate. For example, a file server may be repurchased as SharePoint (see the file server to SharePoint guide), a VM may be rehosted (see VMware to Azure), and an old intranet may simply be retired.

  8. 8

    Evaluate migration tools

    For each workload, list the native vendor tool and any third-party tools, then score them against your requirements in the Migration tool evaluation scorecard: what content types they move, delta sync support, reporting, throttling behaviour and support. Run a small test copy with your preferred tool before committing.

  9. 9

    Compare costs and document the current state

    Fill in the TCO and cost comparison using the vendor's current pricing pages and your real costs. Draw the Current-state architecture so the design team and change board share one picture of today.

  10. 10

    Score readiness and report

    Bring the findings together in the Migration readiness assessment: a score per area (identity, data, apps, network, security, people) and a clear verdict of ready, ready with conditions, or not ready. Present it to the sponsor with the blockers that must be fixed first.

Deliverables

What you produce

DeliverableFree template
Readiness verdict and scoresMigration readiness assessmentXLSX
Application inventory and dependency mapApplication inventory and dependency mapXLSX
Migration path per workloadWorkload 7R decision matrixXLSX
Mailbox, file and data inventoryMailbox and data inventoryXLSX
Current and target licence comparisonLicensing assessmentXLSX
Retention, hold and compliance findingsSecurity and compliance assessmentDOCX
Diagram and description of today's environmentCurrent-state architectureDOCX
Tool shortlist and recommendationMigration tool evaluation scorecardXLSX
Cost of staying versus movingTCO and cost comparisonXLSX
Phase gate

Before you move to Plan

Tick these off with the project sponsor. If any are not true, stay in this phase.

Who is involved

Roles in this phase

RoleResponsibility
Project sponsorSets the business goal, accepts the readiness verdict and decides whether to proceed.
Migration lead or architectRuns discovery, owns the inventory and recommends the path and tool for each workload.
System administratorsExport inventories and reports from mail, file, web and virtualisation platforms.
Application and data ownersConfirm who uses each item, how important it is and whether it can be retired.
Security and compliance leadIdentifies retention, hold, privacy and residency requirements.
Finance or procurementSupplies current licence and contract details for the cost comparison.
Pitfalls

Common mistakes and how to avoid them

Inventory from memory

Export from the systems. People forget the shared mailbox the scanner uses and the share accounting maps at logon.

Ignoring hidden dependencies

Ask "what else stops working if this moves?" for every item, and check service accounts, scheduled tasks, mail relays and hard-coded paths.

Moving everything because it is easier than deciding

Use the 7R matrix to retire or archive stale data and apps. Less to move means a faster, cheaper project.

Losing track of who controls DNS

Confirm registrar and DNS host logins now. Recovering an account owned by a former staff member or agency can take a long time.

Choosing a tool from a feature list alone

Run a test copy with real data and check what did not move before you commit.

Skipping compliance

Find litigation holds, retention requirements and residency rules now. Some block or complicate a move and must be designed around.

FAQ

Questions

How long should a migration assessment take?

It depends on the size and complexity of the estate. A small office with one mail system and one file share can be assessed quickly; a large estate with many applications needs longer. Stop when the gate criteria are met, not at a fixed date.

Do I need a discovery tool?

For mail and files, the admin reports in the source platform are usually enough. For servers and applications, a discovery tool such as Azure Migrate or AWS Application Discovery Service helps find dependencies you would otherwise miss.

What is the 7R model?

A way to give each workload one path: rehost, replatform, refactor, repurchase, retire, retain or relocate. It forces a decision per item instead of moving everything the same way.

What if the assessment says we are not ready?

That is a useful result. List the blockers, assign owners and dates to fix them, and reassess those areas before moving to the Plan phase.